Cromer Estate

Cromer Estate

Delivered for LB Camden

Project introduction

Lawtech undertook cladding remediation works to three 1960s built high-rise blocks situated on the Cromer Estate, Camden.

Cromer Estate.jpg
IMG_2186.JPEG
Cromer Estate (2).png
IMG_2196.JPEG
Cromer Estate (3).png

Location

Camden

Value

£6.3 million

Duration

20 months

Completion

October 2023

Scope

Removal and replacement of combustible cladding

Glynde Reach5.jpg

Facade Solution

The remediation works consisted of the removal of existing cladding and design/installation of replacement cladding to three high-rise blocks on the Cromer Estate, in the Kings Cross area.

The three blocks – and the cladding materials which were replaced – were as follows:

1-48 Glynde Reach

The building was clad with a combination of phenolic EWI and rainscreen cladding.

1-20 Gatesden and 1-38 Bramber House

The blocks were of the same construction type, and were clad with phenolic EWI.

Challenges

“Just-in-Time” Deliveries

To minimise the amount of on-site storage, materials were scheduled to be delivered on a 'just-in-time' basis. Goods/passenger hoists were installed on each scaffold. These were used for the raising and lowering of materials, equipment, waste and personnel.

Protecting Residents

Residents were notified in advance by the RLO when works to their balconies or walkways would be taking place. Access along walkways was closely monitored to ensure resident safety throughout the works.

Traffic Restrictions

As this is a highly populated area, only a short distance from King's Cross and St Pancras train stations, we imposed a 5mph speed limit within the site compound area for all delivery vehicles. Delivery drivers were instructed to contact the Site Manager upon arrival to site, prior to unloading. A trained traffic marshal was present to direct pedestrians and passing vehicles, and delivery drivers were reminded that due care and attention were to be taken at all times.

Resident Liaison/Social Value

Delivering social value means creating positive impacts on communities and enhancing social well-being.

Apprenticeships

Our trainee resident liaison officer (RLO) for this project was recruited from the local community. This provided economic benefits and created an opportunity for them to learn from an experienced RLO.

Wall of Kindness

We also trialled a new initiative over the winter months. With consideration to the amount of foot traffic passing the compound every day, we created a 'wall of kindness' where coats could be donated, accessible to those who may need them. This initiative was a great success, with regular turnover of clothing present on the hooks. We have since scaled this across further sites.